Aluminum Sliding Doors Method Statement

What is the Aluminum Sliding Doors Method Statement?

The aluminum sliding doors method statement installation for any type of building project is outlined below.

Before beginning work on the sliding doors installation, ensure that the material submittal and subcontractor/supplier have been approved.

Ensure that the shop drawings are complete and that the consultant/client has authorized the method of aluminum door fixation and details of aluminum units.

Check that the diameters of the aluminum profiles in the shop drawings are the same as those approved in the material submittals.

The installation of sliding doors should be done in accordance with the manufacturer’s instructions.
Prior to specialists beginning the aluminum doors installation work, all materials must be supplied and made available on-site by the responsible contractor.

Tools and Equipment Required for Installing Aluminum Sliding Doors

Before beginning work on-site, the following tools must be assembled.

  • Rechargeable Concrete Drill Machine
  • Tightening Machine
  • Small cutting machine
  • Wire Extension Line for Tool Box
  • Plastic Dory
  • Hammer
  • Spirit Level
  • Hammer made of metal Star Round
  • flat file
  • Screw Driver Flat
  • Screw Driver
  • Silicon
  • Chisel Right Angle
  • Riveting gun
  • Plier
  • Vice grip
  • Measurement tape
  • Knife
  • Spanner
  • Allen key

The capacity/size of the aforementioned tools and equipment shall be determined by site conditions, requirements, and availability at the time of execution.

See Also: Method Statement for Architectural Works

Requirements for Health and Safety

All equipment, tools, and tackles utilized for the job should be in good operating order and well-maintained.

Personnel will be given a toolbox discussion on how to perform the work safely.

Any employees must complete a safety induction and training course in order to identify any hazards related to this work.

The site’s safety office will carry out risk assessments and update records, which may be inspected at the site office.

All workers/field staff must be given PPE such as coveralls, helmets, safety shoes, safety goggles, safety harnesses, etc.

An aluminum track profile will be cut to length and manually lifted into position on a pre-prepared structure, where it will be secured with screw fixings.

How to Install an Aluminum Sliding Door

This aluminum profile will then be linked to all associated components.

Approved glass door leaves will be physically moved into position and secured to the track.

Activation devices and programmer switches will be put into place and linked back to the operator.

Any remote activation devices/sensors will be placed with cabling that has a minimum range of one meter.

Technicians will make an electrical connection to the operator using the supplied cable (240V 13A) and connect to the BMS/Firefighting System for testing.

The spur should be provided at operator height on the left or right side.

Aluminum sliding doors must be installed in accordance with their working specification

tag: Aluminum Sliding Doors Method Statement