AC Duct Cleaning Method Statement Best for HVAC Ducts and Accessories
The goal of this ac duct cleaning method statement is to eliminate inert suspended materials such as foreign items, molds, and so on. HVAC duct cleaning will be performed until all suspended matter and loose debris from the ducting system have been completely removed.
Before beginning AC duct cleaning works on HVAC ducts, the following tools must be assembled:
Preparation of the Shaft
Works are carried out in shafts and risers on temporary working platforms constructed at each floor level.
During the ac duct cleaning activity, separate safety emergency rescue plans and procedures are prepared for implementation.
Before beginning the AC duct cleaning works, the Site Supervisor and Safety Supervisor must ensure that there is adequate lighting and ventilation.
Prior to beginning HVAC duct cleaning work, ladders or scaffolding must be securely secured over the working platform and checked by a competent person. Site Supervisors must inspect working technicians in risers at regular intervals.
Work Procedure for Cleaning AC Ducts
Prior to the start of work, contractors and people working on other services will be consulted.
Make sure that the access panels are wide open for inserting tools. Some access panels can be employed near VCD, Fire dampers, filter sections, Horizontal duct works, and so forth.
Conduct pre-inspection to verify the exact placement and type of AC equipment, as well as whether additional access points are required.
Before beginning, ensure that the air conditioning system is operational and that there are no abnormalities in sound or noise. If there is an unusual noise, a report should be sent to the building operation management or tenant maintenance before executing the cleaning.
Turn off the air conditioning system or isolate a portion of ductwork.
Place protection beneath furnishings or equipment.
Produce negative pressure by installing specialist vacuum equipment, either within the building with HEPA filtration or outside the building with primary filtering or a monster vac.
Remove grills/vents and plug all openings except the one closest to the vacuum equipment.
Insert the appropriate cleaning tools from the vent/grill further away to loosen the dust, dirt, and debris, which will be drawn away inside the ducts while working toward the vacuum containment equipment.
For longer horizontal distance ducts, cleaning tools must have an extended arm to reach the point where dust, grime, and debris must be manually removed before employing vacuum equipment.
Use plastic sheeting on the ground when moving or mixing cleaning chemicals, unless specialists and manufacturers’ standards demand otherwise.
After portions of supply or return air ducts have been completed, cleaning must be performed with a sanitizer.
Clean and sanitize filters and grills, coils, and drip trays.
For vertical and riser ducts, locate the access door panels again and use specific tools for cleaning and removing dirt, dust, and debris from inside the duct works before using vacuum equipment.
Use the chart and access door schedule established on the ducting system in accordance with approved shop drawings and specifications to access points and locations of access doors and panels.
For large ducts, a person can go inside for cleaning while wearing a safety breathing apparatus and having a time limit of 15-20 minutes to stay inside the ducts to avoid suffocation or an incidental accident during cleaning. – In addition to using SCBA, an appropriate ventilation hood must be placed inside the ducts access opening where the blower fan discharges air inside the large ducts, and after cleaning manually start using the vacuum equipment.
After completing the ac duct cleaning works, immediately close the access panel or access doors.
Ensure that all HVAC duct systems have been thoroughly cleaned, and all reports must be endorsed and signed. Inspection reports must be provided to consultants and witnessed by all parties involved in order to confirm compliance with testing and commissioning schedules.
tag: AC Duct Cleaning Method Statement Recommended for HVAC Ducts and Accessories