Table of Contents
What is the Method Statement of Bridge Load Test?
The Method Statement of Bridge Load Test is a detailed document that outlines the systematic procedure and steps to be followed when conducting a load test on a bridge structure. This method statement typically includes information on the preparation phase, such as site inspection and assessment, equipment setup, and safety measures. It also details the process of applying loads to specific points on the bridge, monitoring instruments, data collection, and analysis techniques. The goal is to evaluate the bridge’s load-bearing capacity, structural performance, and overall stability under different load conditions. Following a well-defined method statement is crucial to ensuring the accuracy and reliability of the load test results while maintaining safety standards and compliance with engineering practices.
Objective
The primary objective of a Bridge Load Test is to assess and verify the structural integrity, stability, and load-bearing capacity of a bridge under different loading conditions. This testing process aims to ensure that the bridge can safely carry the designed loads specified in its engineering plans and standards. Key objectives include:
- Structural Performance Verification: Confirming that the bridge meets the design specifications and performs as intended under various loads, including live loads such as traffic, pedestrians, and other dynamic forces.
- Safety Assurance: Ensuring that the bridge structure can withstand loads without exhibiting excessive deflection, deformation, or stress that could compromise safety during its operational lifespan.
- Compliance with Standards: Validating that the bridge complies with industry standards, codes, and regulations related to load-bearing capacity, structural design, and safety criteria.
- Identification of Weak Points: Detecting any structural weaknesses, vulnerabilities, or anomalies that may require remediation or reinforcement to enhance the overall resilience of the bridge.
- Data for Maintenance and Upgrades: Providing valuable data to inform future maintenance, repair, or upgrade decisions, ensuring the ongoing safety and functionality of the bridge throughout its lifecycle.
By conducting a Bridge Load Test, engineers and authorities can gain confidence in the bridge’s ability to handle various loads, contributing to the overall safety and reliability of the infrastructure.
Scope
The scope is limited to the following:
- Carrying out the pre-test arrangements
- Providing the testing trucks
- Approving the pre-test arrangements
- Installation of the measuring devices
- Supervision of the test and recording the deflection measurements

Bride Design Drawings and Calculations
The bridge static load test depends on applying test load equals to 80% (for the Concrete
spans) and 86% (for the steel span), of the design live load on the those tested spans using a
number of 30 tons in weight trucks as per the design load.
Pre-test Arrangements
Current status of bridge:
Construction and finishing of the bridge are completed
Truck identification and weighting:
Truck dimensions = 7.45 x 2.5m
Truck weight = 30 tons

Installation of measuring devices:
Measuring devices to be fixed at the middle of the tested span on the upper surface.
Mark of truck location:
The middle point of each lane to be marked on the upper surface of the bridge.
Trucks to be arranged as per the loading layout
Loading Procedure
Temperature measurement
Degree of Temperature should be measured and recorded before and during the test
for the atmosphere.
Loading sequence
The tested span will be loaded on stages as per the loading layout considering the
following:
- Start loading from edge row then the adjacent row;
- Keep one hour time period before loading the next row;
- Unloading all the rows 6 hours after loading the last row.

Deflections, and temperature monitoring procedure
All readings to be recorded as follows:
Before loading:
Just after applying each loading step;
One hour after applying the full load for six hours;
Just before and after unloading:
Every half hour after unloading for 2 hours
Loading Test Analysis
Results shall be graphed (deflection vs. load) for loading and unloading
Maximum deflection shall be compared with the design requirements
Residual deflection shall be compared with design requirements and codes.

Risk Assessment and Mitigation Plan
In order to assess the risk of bridge failure during loading test, the deflection readings to be
instantly compared with the pre-calculated theoretical design values, the test should be
terminated and the tested span to be immediately unloaded if the observed deflection values
exceeded the calculated ones.
Comparison Procedure Between Test Results & Design Values
A comparison between test and design results deflection shall be summarized in tabular and
graph forms for each loading step at start, mid and end of tested girder.
FAQs
Why is a method statement essential for a Bridge Load Test?
A method statement provides a systematic and organized approach to conducting a Bridge Load Test, ensuring consistency, safety, and adherence to engineering standards. It outlines step-by-step procedures, minimizing errors and enhancing the reliability of test results.
What safety measures are typically included in a Bridge Load Test method statement?
Safety measures commonly outlined in a method statement include securing the work area, implementing proper signage, ensuring personnel wear appropriate protective gear, and following established protocols to prevent accidents or injuries during the testing process.
How is the load applied during a Bridge Load Test, and what instruments are used for monitoring?
The method statement details the specific process of applying loads to designated points on the bridge, often using hydraulic jacks, loaded trucks or other specialized equipment. Instruments like strain gauges, displacement sensors, and load cells are employed to monitor the bridge’s response to the applied loads accurately.
What factors are considered in the analysis phase of a Bridge Load Test method statement?
The analysis phase typically considers factors such as deflection, strain, and structural response under different load conditions. The collected data is then compared against design specifications to assess the bridge’s load-bearing capacity and overall structural integrity.
Can a Bridge Load Test method statement be customized for different bridge types?
Yes, method statements are adaptable to various bridge types, considering factors like design, materials, and construction methods. Customization ensures that the testing process is tailored to the specific characteristics of the bridge under examination, enhancing the relevance and accuracy of the results